EKHOMBE HOSPITAL
Construction of 37 Nurses' flats and 3 Doctor's houses.
Client: Independent Development Trust
Principal Agent: Delexc.
Duration: 18 months
Value: R21 300 000
SINQOBILE ECDC
Construction of early childhood development classrooms.
Client: Independent Development Trust
Principal Agent: Delca Systems
Duration: 5 months
Value: R4 700 000
FORT NAPIER HOSPITAL
Maintenance and refurbishment to the hospital
Client: Independent Development Trust
Principal Agent: Delexc
Duration: 12 months
Value: R13 400 000
MOSVOLD INGWAVUMA CLINIC
Client: Independent Development Trust
Principal Agent: Architronic Architects
Duration: 18 months
Value: R9 300 000
MBUTHISWENI PRIMARY SCHOOL
Client: Coega Development Agency
Principal Agent: Excellence
Duration: 18 months
Value: R8 000 000
SUNDUMBILI CHC
Maintenance and renovations to the clinic
Client: Department of Public Works, Mayville
Principal Agent: Jeremy Steere Architects
Duration: 9 months
Value: R6 600 000